You’re faced with quite the challenge – that road batter is a crucial element in your road construction project and the exposed surface is going to need revegetation.

Rubber Duckies and Positracks are great, but you need to shift volume and access is generally a nightmare.

This is where the PMB TR20 Slinger becomes your new favourite solution for batter slopes.

Batter Slope • Road Batter • Soil placement using PMB Slinger in Western Australia • Perth Materials Blowing

How do we achieve this?

The PMB TR20 Slinger is the perfect tool for the job.

Super-specialised, this machine installs topsoil and topsoil/mulch blend like nothing else.

It can even ‘throw’ it into position – removing any need for machinery to access those ‘impossible’ embankments.

The TR20 is better than any other method you’ve ever used.

Our TR20 Slinger is designed with this challenge in mind – easy positioning for inaccessible slopes, installs topsoil at considerable distances and does it quicker than any other solution you have previously used.

Batter Slope • Road Batter • Soil placement using PMB Slinger in Western Australia • Perth Materials Blowing

How safe is it?

It’s all about the right tool for the job: PMB’s TR20 Slinger eliminates the need for a Positrack to drive on a steep slope, removing any safety risk of a machine rolling over or the slope collapsing.

The TR20 Slinger comes into its own as it is 100% remote control operated – allowing the Operator to be located in the perfect position to see the entire work zone and place material safely into the correct location.

Our TR20 Slinger significantly alleviates OSH concerns for project managers when faced with a slope gradient that is simply too steep. It installs topsoil at safe distances without having to operate on the slope itself. Total operational control is achieved at safe distances.

Road Batter Yanchep Rail Extension • Soil relocation & spreading at distance using PMB TR20 Slinger in Western Australia • Perth Materials Blowing

How fast and how much?

The short answer is easy: How fast can you load us?

The TR20 Slinger can install up to 3t of material a minute.

Or in a single day? Up to 1,000 tonnes.

Batter Slope • Soil installation at distance using PMB Slinger in Western Australia • Perth Materials Blowing

How far away?

The TR20 Slinger can ‘throw’ soil from 5-40m away – literally allowing an embankment slope to be topsoiled without any machinery driving on it.

Our fully remote-control operations give us both options and every distance in between. That’s how we achieve distance plus accuracy.

Batter Slope Revegetation – Factor It In Early

Taking batters into consideration early in the road construction is a low cost strategy when you compare it to the less-favoured, and far more costly alternative.

At the construction project’s completion, cut batters of land are exposed earth surfaces facing a risk of rapid erosion unless soils and mulch are installed on these steeper constructed slopes.

Consideration of good drainage, soil type, the soils installation before and during the earthworks and construction of batters is critical, thereby preventing that added cost of erosion repair – a direct result of you stalling on revegetation until the project’s end.

And that’s too late.

Don’t take our word for it – it’s all there in black & white on the Main Roads Western Australia Specification 304 Landscaping and Revegetation:

Timing of Works • The revegetation and landscaping works must commence as early as practicable after completion of the earthworks, and within the optimum time of year as nominated in Annexure 304B, to minimise soil erosion and ensure the effective revegetation of all disturbed soil areas. 

Don’t leave it until the end of the project. Get in contact with us early.

Planning for the Installation Period

It is stated clear and upfront in the Spec 304 that skilled personnel that are considered a Contractor’s sole responsibility under their supervision must be:

competent, experienced, and skilled in all aspects of the required landscape installation and establishment practices.

Partnering with PMB early in your process and deploying the TR20 Slinger fulfils this criteria when it comes to providing immediate erosion control and batter revegetation – our experience and cutting-edge equipment ensures this.

Batter Slope Products & Materials For Installation

Whether it’s topsoil or mulch as required by the Spec 304, PMB has hard-won experience in installing all of these and can even supply to AS standards.

Insitu Topsoil • all cleared topsoil stockpiled on site (see Specification 301) that has been designated for re-use as topsoil.

Imported Topsoil • imported material for use as topsoil must comply with AS 4419. That’s good news for you because all of PMB’s premium soil products are Australian standard AS4419-certified for quality and are designed for fast installation.

Stockpiles of Topsoil or Mulch • preparing and managing all stockpiles is that much easier with the PMB Slinger and Blower fleet. In fact, using our fleet means stockpiles are relocated, reduced and in many cases eliminated.

Imported Composted Mulch • must comply with AS 4454. Again, that’s good news for you as the contractor because PMB offers a wide selection of high quality, AS4454 compliant mulches suitable for civil and government landscaping projects. So it’s a double whammy – we can supply and then install for you.

Preparation of Road Batter Surface • Topsoil Respread

Timing • any topsoil, whether approved site suitable or PMB-supplied, must be respread quickly subsequent to construction operations, to maintain weed control and minimise soil erosion. The TR20 Slinger is the best tool for this as it handles the identified spoil (which must be spread first), followed by the topsoil.

Respreading Topsoil • this is where the TR20 Slinger comes into its own, as topsoil must be uniformly spread over the length of the road batter surface according to depth and levels shown in the Drawings. There is no easier way than with our slingers.

Topsoil Depth • unless the Drawings or Spec 304 Annexures indicate otherwise, a nominal depth of 75-100mm of topsoil must be placed prior to planting. This is what PMB specialises in, our teams working with and support you to calculate expected material volumes and placement in accordance with the specs.

Road Batter Surface • Soil Improvements

Part of our daily soil installation processes will involve soil and drainage improvements.

If the Drawings or 304 Annexures call for Soil Conditioner and Additives, we can easily work with you to determine how to incorporate into the surface layer of topsoil in preparation for seeding and planting, in many cases as part of the initial install.

No need to come back to do this as an additional step – there’s some more cost savings for you.

If the Drawings or Spec 304 Annexures demand, improvement of sandy soil surfaces must incorporate chipped vegetation mulch and that it must be spread on the soil surface to the nominated depth with suitable equipment.

The suitable equipment referenced? It wouldn’t get any better than our Slinger and Blower fleet, which places that mulch at distance, with precision, and to nominated depths. Problem solved.

Batter Slopes Erosion Control • Matting & Geotextiles

It’s worth mentioning at this point that building a road batter structure will often call for matting sheets, geoweb, or soil containment cells to be applied over embankments once construction works are completed.

PMB has worked with all three of these erosion and soil stabilisation materials on prior projects, which makes us the go-to for installing topsoils and mulch to fill to the nominated depths the Drawings and Annexures specify.

Partners and Affiliations

Preparation of Road Batter Surface • Mulch Spread To Avoid Soil Erosion

Some projects will call for approved mulch to be spread once excavation, surface preparation, topsoiling, soil improvements, or erosion control matting is complete.

What you’re trying to avoid here is overland flows from a rainfall event that creates soil erosion. At that point you, as the Contractor, would be responsible for replacing the eroded material and preparing the soil surface before mulch spreading can commence.

You don’t want that additional cost, even if the chances of flow from a rainfall event are slim.

Here’s where our PMB fleet can get the job done for you in line with the Spec 304.

See our Mulch Blower on a major Civil Construction project

Mulch Depth • a nominal depth of 75-100 mm of mulch must be placed (If not specified in the Drawings or Annexures). Same as for topsoil, this is PMB’s specialty, and we will calculate material install volumes & placement strategy with you.

Even Depth of Mulch • the Spec 304 is really specific about this one:

Mulch must be uniformly spread over the ground surface to an even depth by hand, machine or blower unit and if required the surface raked to present an even surface.

By hand? Forget it.

By machine or blower unit? Now we’re talking.

If the Slinger is perfect for topsoil respreading, then it’s our Blower Trucks that are perfect for the mulch spread phase of your project.

Installing mulch at 30m3 per hour, at close proximity or distance, and with uniformity and consistency eliminates the requirement to rake for that essential even surface.

See our Mulch Blower on Batter Works

Avoid Mixing Mulch • Unless the drawings specify otherwise, mulch must not be mixed in with the in situ soil or buried in between layers of the soil during the spreading operations.

No chance of that when you use PMB. The Slinger will install the in situ and supplied soil, then the Blower Trucks install the mulch. A combination of different material inputs utilising different fleet machinery.

Avoid Over Spreading Mulch • This is the clincher and we’ll quote the Spec 304 verbatim here to make the point:

The Contractor must avoid spreading mulch on plants, structures, roadways, and paths, road shoulders and grassed areas and leave the site in a neat, clean condition.  Mulch must not be placed closer than 250 mm from the stem of any existing vegetation or new plantings.  Existing vegetation or new plants accidentally covered by mulch must be uncovered as soon as possible.

This is exactly why landscapers, developers, civil construction and government call on PMB. To install (spread) mulch to these kind of detailed and precise specifications:

  • DON’T spread mulch on plants, structures, roadways, paths, shoulders and grassed areas
  • DO leave the site in a neat, clean condition
  • DO install mulch away from vegetation and new plantings

All the above is baked into our processes. It’s our standard, not an exception.

This is how our PMB Blower Truck fleet works and why we should be your preferred partner in your next road batter project.

Contact Us Now

We’ll work with you every step of the way to ensure all of PMB’s landscaping and revegetation works meet the completion criteria and detail as specified in the Spec 304 Annexures, including:

  • 304B.3 – Topsoil Respread Requirements

  • 304B.7 – Mulch Requirements

  • 304B.8 – Surface Preparation and Soil Improvements

  • 304B.9 – Erosion Control Requirements

  • 304B.11 – Timing Of Works

  • 304C.6 – Erosion Control

  • 304C.11 – Regeneration From Topsoil

CASE STUDY

THE DETAILS

PROJECT: Yanchep Rail Extension

TOTAL PROJECT BUDGET: $1.082 billion

EXPECTED DELIVERY DATE: late 2024

STAGING INVOLVEMENT FOR PMB: Main Construction Works

JOB TYPE: Topsoil Embankment

CLIENT: New East Alliance and METRONET

DATE OF WORKS: November 2023 – ongoing

SERVICES: Slinger

THE PROJECT

METRONET hired PMB to complete 10,000+m3 of soil backfilling works on the 14.5 kilometre Joondalup Line extension, which plays a vital part in dealing with the future growth of Perth’s northern suburbs.

This job was only the second deployment of the TR20 Slinger straight out of commissioning, and has been supplied onsite as a wet hire with our trained operator for the duration of the railway embankment stabilisation.

PMB’s role is part of the main construction works, the longest of the project phases. Elements of this stage include bulk earthworks, drainage works and track laying.

THE CHALLENGE

As we’ve outlined above, the main challenge was soil installation across cut batters, including both exposed earth surfaces and maintenance of areas previously backfilled.

Access for any earthmoving equipment onto the slopes was not a consideration due to its steepness.

Which is where the PMB TR20 Slinger came into its own.

THE PMB SOLUTION

This is our wheelhouse.

The PMB Slinger was able to shoot the soil at distances exceeding 30 metres, all the while being reloaded with site-won materials by onsite excavators, providing a seamless and uninterrupted workflow that saw hundreds of cubic metres of topsoil/mulch blend thrown into place each and every single day.

No other piece of kit is capable of that level of work, with precise installation completed quickly.

Our expert operator became an indispensable asset for our client as he was able to control the slinger and its slinging angle remotely, progressing the slinger effortlessly along the length of the rail embankments.

No safety issues presented themselves as the Slinger was remotely operated, ensuring safety for not only our crew member, but also our client’s team.

There’s always a learning curve on every project and being onsite for the duration, our Operator became an expert in what was required to complete the job.

The result has wowed our client, and they are keen to utilise our Slinger again for its upcoming roster of projects.

Road Batter Planting • The Payoff

This is where the hard work we’ve done together produces a dividend – the planting process can commence and the chances of a successful client handover (and continued vegetation period) increase exponentially.

Before planting, a Hold Point is likely to kick-in and assess:

  • Soil moisture confirmation at a minimum 100m depth
  • Risk of surface runoff flow

By attending to the topsoil and mulch spreading outlined earlier, the likelihood of a reduction in Hold Point time occurs. The already applied materials aids soil moisture retention and erosion control. Planting can get underway without delay.

Batter Slopes Handover • Final Completion

Tidying Up • Prior to works completion, the following two safety criteria (amongst others) must be met:

  • all surplus materials must be removed from site.
  • the Site must be left in a neat and tidy condition.

When you deploy PMB’s expertise, we certainly wouldn’t be a factor in this problem:

  • surplus topsoils or mulches aren’t likely – we will have relocated stockpiles and installed in situ topsoil, and additional topsoil and mulch supply will have been installed to pre-determined volumes without wastage
  • ·a neat and tidy condition is how we finish every job – it’s our standard. Plus the precise blowing, slinging and throwing ensures there was no mess to begin with

Are your Batter Earthworks already complete?

So, your batters are long since constructed, and now you realise you need some help with materials installation. Can we still help you?

Our ideal solution is not to be parachuted in at the last minute – we believe in a work smarter not harder approach that would have us involved from the design and implementation stage, that’s ultimately the gold-standard outcome for us both.

Having said that, of course we can still be your partner on this!

Get In Touch

Fast Installation • Gauge • Design Icon • PMB • Perth Materials Blowing

Fast Installation

Up to 1,000 tonnes in a single day

Seamless and uninterrupted workflow

The TR20 Slinger can thrown 100m+ of soil into place each and every single day

That’s 500m3 of soil in a regular working week

Proximity or Distance • Design Icon • PMB • Perth Materials Blowing

Proximity AND Distance

The TR20 Slinger installs soil from 5-40m away

No machinery required to drive on embankment slopes

Fully remote-control operations

That’s how we achieve distance plus accuracy.

Batter Slopes • The PMB TR20 Slinger is the perfect tool for the job

A super-specialised piece of kit to finish off your earthworks and road construction unlike anything else.

Our Slingers, used in conjunction with our Mulch Blowers, is superior than any other method you’ve ever used.

Get in contact with us right here.

Let’s produce results in a way you never have on your civil construction projects across Perth and Western Australia.